Bathroom Renovation Quotation in Singapore: What to Compare Line by Line Before You Choose a Contractor

Guide · By Larry Hoo, HDB Licensed Renovation Contractor ·
Bathroom Renovation Quotation in Singapore: What to Compare Line by Line Before You Choose a Contractor

Pictured above: a finished bathroom with a white countertop basin, brass tap, arched mirror and louvred door, from our project archive (C05).

You have three bathroom quotes on the table. One is a single line, "bathroom renovation, full set, lump sum". One runs to a page. One is cheaper than the other two by a margin that makes you nervous. The question is rarely "who is cheapest". It is "are these three quotes pricing the same job?" Usually they are not, and the differences sit in lines that are easy to miss.

This guide is for the homeowner choosing between bathroom renovation contractors in Singapore. It uses only what we publish on our bathroom renovation page, and tells you what to ask where a figure is not published.

Start with the range, so you know when a number is odd

Our published guide gives an HDB bathroom, common or master, at $5,000 to $12,000, with a full hack-and-retile including new toilet, basin, mixer, shower, vanity and waterproofing typically between $7,000 and $10,000. Master bathrooms with rain showers and double basins sit at the higher end. A condo bathroom is $8,000 to $20,000 and a landed bathroom $10,000 to $25,000 and up.

A range is not a price, and it is not a promise that your quote will land inside it. What it does is tell you when to ask a question. A quote far under the range for a full hack-and-retile has either left something out or priced something thinner. A quote far over it should be able to tell you which line is carrying the extra.

The lines a bathroom quote should show separately

Our quotations itemise six things separately: the waterproofing, the tile cost per square metre, the sanitaryware, the vanity, the accessories and the labour. You can compare any other quote against that list. If a line is missing, ask whether it is included or simply not mentioned.

Where the cheap quote usually saves its money

If one quote is well below the others, the saving is usually in one of four places, and you can ask about each in a single message.

  1. The ponding test is quietly dropped. Some contractors waterproof and tile in the same week to compress the schedule. If the membrane has a pinhole, you only find out years later when water seeps into the unit below. A 24-hour test costs a day on the schedule, which is why it is the first thing to go when a contractor is trying to be fast or cheap.
  2. The floor is re-used. Re-using the existing trap and floor gradient saves hacking and screeding. It also keeps the problem you were renovating to get rid of.
  3. The tiles are only half-height. Less tile, less labour. The walls left bare behind the basin and shower discolour and crack within three to five years in our experience.
  4. The fittings are the cheapest on offer. Not wrong in itself, but then the quote should name them, so you are comparing like with like.

The timeline is a line item too

A typical bathroom remodel takes 2 to 4 weeks per bathroom. If you are renovating more than one bathroom in a single project, they usually run in parallel without extending the overall duration much. Our published sequence for one bathroom runs hacking, then plumbing and electrical re-routing, then waterproofing, then the 24-hour ponding test, then screed and tiling, then sanitaryware, vanity and mirror, and finally the false ceiling, lighting, cleaning and handover.

Ask each contractor for their own sequence with dates. A contractor whose sequence has no gap for the ponding test between waterproofing and tiling is telling you something about the quote. If you live in the flat and it has only one bathroom, the sequence is also your plan for where the household showers, so ask before you sign, not after hacking has started.

Working hours you should know before you compare timelines

HDB allows renovation work 9am to 6pm on weekdays and 9am to 1pm on Saturdays, with no work on Sundays or public holidays. Condos are usually stricter: common conditions include weekday-only working hours, a deposit and noise restrictions, so read your MCST house rules. A contractor who promises a schedule that cannot fit inside these hours has not read them.

A side-by-side you can do in ten minutes

Make a table with one column per quote and one row for each item above. Mark each cell as "named", "included but vague" or "not mentioned". Anything "not mentioned" gets one question to the contractor. The quote that answers all of them clearly, with the waterproofing and ponding test in writing, is usually the one to take forward, even if it is not the cheapest.

If you want the broader method for any quotation, our guide on how to read and compare renovation quotations covers the whole-flat version. For the single-room case, see renovating one bathroom on its own, and for the test that proves the waterproofing, the ponding test and what to ask before tiling.

The short version

We are an HDB Licensed Renovation Contractor, HB-09-5667H. Want a bathroom quoted line by line? WhatsApp us on 9107 2601 with your property type, estate and which bathroom it is, and attach photos of the room. Full scope and pricing is on our bathroom renovation page.

Frequently asked questions

How much does a bathroom renovation cost in Singapore?
Our published guide gives an HDB bathroom, common or master, at $5,000 to $12,000, with a full hack-and-retile typically between $7,000 and $10,000. A condo bathroom is $8,000 to $20,000 and a landed bathroom $10,000 to $25,000 and up. The exact quote follows a site visit.
What should a bathroom renovation quotation list separately?
Our quotations itemise the waterproofing, the tile cost per square metre, the sanitaryware, the vanity, the accessories and the labour separately, so you can compare line by line. If a line is missing from another quote, ask whether it is included or just not mentioned.
What waterproofing should a bathroom quote specify?
Our specification is two coats of approved membrane on the full floor and 1.5m up the wet walls, followed by a 24-hour ponding test before any tiling begins. Ask for the coats, the wall height and the test in writing on every quote you compare.
How long does a bathroom renovation take?
A typical bathroom remodel takes 2 to 4 weeks per bathroom. Several bathrooms in one project usually run in parallel without extending the overall duration much. Ask each contractor for their own sequence with dates, including the gap for the ponding test.
Why is one bathroom quote much cheaper than the others?
Common places a low quote saves money are a skipped or shortened ponding test, re-using the old floor trap and gradient, half-height tiling and the cheapest fittings. Ask each contractor about those four points in one message and compare the answers.
Larry Hoo — HDB Licensed Renovation Contractor (HB-09-5667H)

Larry Contractors Pte Ltd · 15+ years · 500+ projects · own carpentry factory in Singapore. Read more about Larry →