Washing Machine and Laundry Area in an HDB Flat in Singapore: Where the Drain, Tap and Socket Must Go Before Tiling

Guide · By Larry Hoo, HDB Licensed Renovation Contractor ·
Washing Machine and Laundry Area in an HDB Flat in Singapore: Where the Drain, Tap and Socket Must Go Before Tiling

Pictured above: a front-loading washing machine standing on a raised drawer base beside the sink in an HDB kitchen, from our project archive (407B). Look at the wall to the right of the machine: the water tap and the hose are in plain view, and the drawers under the machine pull out. Positions like these are fixed in the wall, the floor and the carpentry drawing long before the machine is carried in.

Most people choose a washing machine the way they choose a fridge: late, and for the features. The renovation has usually finished the walls and floor by then, and the machine goes wherever the pipes happen to be. In a flat that has been renovated without anyone asking where the machine goes, the pattern is familiar. The tap is behind the machine, the waste hose is stretched across the floor, the socket is out of reach, and the only way to fix any of it is to break something that was only just finished.

This guide is for an HDB owner planning the washing machine, or a whole laundry corner, during a renovation. It uses only the rates and the programme already published on this site. It does not tell you which machine to buy or how much a tap or a waste point costs, because we do not publish prices for those and they depend on your flat. What it covers is the part a contractor can tell you: what has to be settled, in which week, and what to ask before anything is covered up.

The short answer

A washing machine needs three things in the same place: water in, water out and power. Choose the machine, or at least the type of machine, before the plumber and the electrician start. Put the tap, the waste point and the socket where the machine will actually stand, at the height it will actually stand at, with the tap reachable. Do it before the waterproofing and the tiling, because after that every change means breaking finished work.

Step one: decide the machine before you decide the corner

Where the machine can go depends on what it is. Settle these first, and write the answers down for your contractor.

  1. Front-loader, top-loader or a washer and dryer stacked. A front-loader needs room for the door to swing open and for you to bend to it. A top-loader needs clear space above it for the lid. A stack is tall, and it changes the height at which the tap, the waste and the socket should sit.
  2. Standing on the floor or on a base. The photo above shows a base with drawers. A base brings the machine up to a height that is easier on the back and gives you storage, but it changes every height in the next section.
  3. Inside the kitchen, in the service yard, or in a cupboard. Each has a different answer to where the water goes if something leaks, and we come to that below.
  4. The model, if you can. Every washing machine comes with an installation sheet that gives the water inlet position, the length of the hoses, the maximum height of the waste hose and the electrical requirement. We do not publish those figures, because they are different for every model. Ask the shop for the sheet, or at least for the model number, and give it to your contractor and electrician before first fix.

Step two: the tap, where the water comes in

The tap that feeds the machine is a small fitting in the wall and the most commonly misplaced thing in the corner.

Step three: the waste, where the water goes out

This is the one that is hardest to change, because the waste runs under or inside what is finished last: the floor.

Waste runs work on gravity and fall, nothing else, so a waste point is one of the least flexible things in a flat. That is why we say to settle it before the layout is agreed, not after the tiles are chosen.

Step four: the socket

The machine has to be plugged in, and the socket has to be where the machine can be reached, not where it is convenient for the wall.

Where it sits in the programme

On our published 4-room programme, a full renovation runs like this.

Three things follow. First, the machine decision has to be made before week 2, and not when the machine is delivered. Second, a base or a cupboard built in carpentry is installed in weeks 6 to 7, after the pipes are buried and the tiles are down, so the pipes have to be placed for the finished carpentry, not for what is there when they go in. The carpenter measures late; our post on when the carpenter should measure explains why, and the order in which trades follow each other is in the order of works post. Third, carpentry is built in a factory to the drawing, so the drawing has to show the machine, the base, the tap and the socket together before it is signed.

The carpentry rate we publish is $400 per foot run, for runs up to 2.6 m high and 650 mm deep. We do not publish a separate price for a washing machine base or cupboard, so how it is measured and priced is for the site visit.

Waterproofing: the reason this has to be early

Every pipe or socket box that comes through a waterproofed floor or wall is a hole in the thing that is meant to keep water in. Our room cost calculator treats a service yard as a wet area, and its tiling rate of $11.80 per sqft is labour including waterproofing and a 24-hour ponding test for wet areas. The order that works is the one we describe in our guide to the ponding test before tiling: pipes in and final, waterproofing applied, tested, and only then tiling. If a waste point or a socket is added after the test, somebody is cutting into a membrane that has already been proved, and nobody retests it.

Hacking and plumbing are quoted as a lump sum on the free site visit, because they depend on your existing layout. So the price for moving a washing machine point in your flat is also for that visit, not a number we can give you here.

Questions to put on the quotation

  1. Which machine, or which type of machine, is this drawn for, and have you seen its installation sheet?
  2. Where are the tap, the waste point and the socket on the drawing, and at what height from the finished floor?
  3. Are those heights for the machine on the floor or on a base?
  4. Can I reach the tap to turn it off without moving the machine?
  5. If the hose comes off or the machine overfills, where does the water go?
  6. Is the socket a standard power point, and is it priced as one?
  7. Is the waste point in place and final before the waterproofing is done?
  8. What happens to the price if I change the machine after the drawing is signed? (A change after the drawing is signed is a variation order; see our post on variation orders.)

What to do this week

  1. Decide the type of machine and where you want it, and write down whether it is on the floor or a base.
  2. Ask the shop for the installation sheet, or at least the model number.
  3. Photograph the corner where the machine is now: the tap, the waste, the socket and the floor trap.
  4. Take the photographs and the sheet to your contractor before first fix, and ask for the three positions to be shown on the drawing.

We are an HDB Licensed Renovation Contractor, HB-09-5667H. Planning where the machine goes? WhatsApp us on 9107 2601 with your flat type, your estate and the type of machine, and we will arrange a site visit to look at the tap, the waste point and the socket. Any price depends on that visit. The published programme and figures are on our 4-room HDB renovation cost page, you can run the published electrical and tiling rates on the room cost calculator, and our other services are on the HDB renovation contractors page.

Related reading: plumbing work and the licensed plumber · ponding test before tiling · order of works

Frequently asked questions

What does a washing machine need in an HDB flat?
Three things in the same place: a water tap, a waste point (or a hose to a floor trap) and a power socket. All three are fixed during the plumbing and electrical stage, which on our 4-room programme is weeks 2 to 3, well before tiling in weeks 4 to 5 and carpentry in weeks 6 to 7.
Why decide the washing machine before the renovation starts?
Because the tap, the waste and the socket are set at a height and a position that suit one particular machine. A front-loader, a top-loader and a stacked washer and dryer need different heights, and a machine on a base needs different heights again. Moving any of them after the floor is waterproofed and tiled means breaking finished work.
How much does it cost to add or move a washing machine point?
We do not publish a price for it. Our room cost calculator lists $90 for a power point and $90 for a light point, and quotes hacking and plumbing as a lump sum on the free site visit because they depend on the existing layout. The price for your flat is given after a site visit.
Should the washing machine tap be reachable?
Yes. You should be able to turn it off without moving the machine, so it should not sit behind the machine or behind a fixed carpentry panel. Set its height for the machine as it will actually stand, on the floor or on a base.
Is a service yard waterproofed?
Our room cost calculator treats a service yard as a wet area, so its tiling rate of $11.80 per sqft is labour including waterproofing and a 24-hour ponding test for wet areas. Any waste point or socket box in that area should be in place before the waterproofing is applied and tested.
Larry Hoo — HDB Licensed Renovation Contractor (HB-09-5667H)