Kitchen Sink and Tap in an HDB Kitchen, Singapore: Undermount or Top-Mount, Where It Goes, and What to Settle Before the Worktop Is Cut
Pictured above: a kitchen run in one of our HDB maisonette projects. A single-bowl stainless steel sink is set under the worktop, a tall swan-neck tap stands at the back edge, a dish rack and a small countertop appliance sit beside it, and the induction hob is further along. A double socket sits on the splashback. Every one of those positions was fixed before the worktop was cut.
The kitchen sink looks like the last thing you need to think about. It is one of the first. Its waste pipe and water points go in with the plumbing, weeks before the cabinets arrive, and its cut-out is made in the worktop to the shape of the actual sink. If the sink and tap are still "we'll choose later" on those two days, somebody guesses, and a guess in a pipe or a stone worktop is expensive to undo.
This guide uses only figures already published on this site.
The short answer
- Choose the sink and tap by model before the plumbing starts. The waste, the cold and hot water points and any wall-mounted tap are fixed then.
- Keep the sink near where the waste already is, unless moving it is worth the extra plumbing. The further it moves, the more the pipe has to travel, with a fall.
- Undermount or top-mount is decided with the worktop, not after it. An undermount sink goes in with the worktop. A top-mount sink sits on it and is easier to change later.
- Have the sink on site, or its exact model fixed, when the worktop is measured. The cut-out and the tap hole follow the real sink, not a catalogue picture.
When the sink is decided: twice, weeks apart
On our 4-room HDB renovation cost page, hacking is week 1, masonry, plumbing and electrical are weeks 2 to 3, waterproofing and tiling are weeks 4 to 5, and carpentry is weeks 6 to 7. That order is why the sink catches people out. It is decided twice.
The first time is the plumbing, in weeks 2 to 3. The waste outlet and the water points are set into the floor and wall, and then the kitchen is waterproofed where needed and tiled over them. After that, a point that is in the wrong place means opening a finished wall or floor.
The second time is the worktop. A worktop is measured after the base cabinets are fixed, because it has to follow what is really there, not what was drawn. The sink cut-out and the tap hole are made to that measurement. Our guide on when the carpenter should measure goes through that order for the whole kitchen.
On that published programme the two dates are several weeks apart. Owners often use that time to shop for the sink. By then the pipes are already in.
Where the sink goes
In most HDB kitchens the sink is already on a sensible wall, often under the window, with the waste close by. Leaving it there is the cheapest choice.
Moving it along the same run is common and usually manageable. Moving it to another wall, or onto an island or a peninsula, asks more: the waste has to run further with enough fall, and the floor may have to be built up to carry it. Our guide to an island or a peninsula in an HDB kitchen covers what a sink on the counter asks of the floor.
We do not publish a price for moving a sink. Plumbing is quoted as a lump sum after a site visit, so show us where you want it and ask for the move as its own line on the quotation.
Three checks on position, whatever you choose:
- The working order. Stand where you cook. Fridge, sink and hob should follow the way you work, with some clear counter on both sides of the sink for dirty and clean dishes.
- The window. If the sink is under the window, check that the tap you want clears the window when it is opened, and that you can still reach the window handle over the sink.
- The corner. A sink pushed into a corner leaves little room to stand. Ask to see the drawing with the bowl drawn in.
Single bowl, double bowl, or a bowl with a drainer
An HDB kitchen counter is not long. A double bowl or a bowl with a drainer takes counter length that would otherwise be work space between the sink and the hob. A large single bowl takes a wok or a big pot more easily. Choose the bowl before the drawing is signed, because the size of the bowl decides the width of the sink cabinet under it and the cut-out in the worktop.
Undermount or top-mount
An undermount sink is fixed under the worktop. The edge of the worktop runs straight into the bowl, so you can wipe crumbs and water straight in, and there is no rim to collect grime. It goes in with the worktop, so it must be on site the day the worktop is fitted. Because the cut edge of the worktop is left exposed around the bowl, it is normally paired with a stone or quartz top. If your worktop is laminate, ask how that edge would be sealed, or choose a top-mount sink.
A top-mount (drop-in) sink sits in a cut-out with its rim resting on the worktop. The rim covers the cut edge and is sealed along it. It can be fitted after the worktop, and it is the easier one to replace years later. The trade-off is the rim, which needs cleaning along its edge.
Either way, the cut-out is made to that sink model.
The tap: on the worktop, on the wall, or with extras
- A deck-mounted tap stands on the worktop or on the sink's own tap hole. The hole is cut with the worktop, so the tap's position is fixed when the worktop is measured.
- A wall-mounted tap needs its pipe in the wall at the plumbing stage, at the right height above the worktop and the splashback. That is weeks 2 to 3, long before the worktop exists, so the height must come from the actual tap and the actual worktop height.
- Hot water at the kitchen sink needs a hot water pipe run to the sink from the heater. Decide it at the plumbing stage. If you are changing the water heater as well, our guide to instant or storage heaters and the 20A point covers that side.
- A water filter, or any appliance under the sink that needs power, needs space in the sink cabinet and, if it is electric, a socket placed at the electrical stage. On our room cost calculator an ordinary power point is $90 and an isolated power point is $150.
The sink cabinet and the dish rack
The cabinet under the sink takes more water than any other box in the kitchen. When we look at old kitchens, the base panel of the sink cabinet is the first place to check: a panel that is soft, swollen or flaking at the edge has been taking in water for years. On a new kitchen, ask three things about that one cabinet: what the base is made of and how its cut edges are sealed, how the shelf is cut around the waste and pipes, and whether the water stop valves can be reached without taking anything apart.
Then the dish rack. You can stand one on the counter, as in the photo above, or build a dish rack into the wall cabinet over the sink so that it drips into the bowl. A built-in rack changes how that wall cabinet is drawn, so it is a carpentry decision, not a shopping one. Say which you want before the drawing is finished.
What our published figures cover, and what they do not
These are lines we already publish. They are estimates, and the final price follows a site visit.
- On our room cost calculator, a tabletop or countertop is $150 per ft run for up to 650mm depth, and carpentry such as kitchen cabinets is $400 per ft run, up to 2.6m height.
- On our HDB renovation cost pages, a full kitchen cabinet set of around a 4-metre run is $3,500 to $8,000.
- As a standalone package, a kitchen renovation is $8,000 to $25,000: basic ($8,000 to $12,000) covers re-tiling, painting and replacing the hood and hob; standard ($12,000 to $18,000) adds new laminate cabinets and a quartz countertop; premium ($18,000 to $25,000) adds sintered stone, soft-close hardware and integrated appliances.
- Hacking, plumbing and sanitaryware are quoted as a lump sum after a site visit, because they depend on the existing layout and condition.
What we do not publish: a price for the sink or tap themselves, for moving a sink, or for a new hole in a finished worktop. Those are priced after the visit.
Questions to put in writing
- Which sink and tap are priced, by model, and are they supplied by you or by me?
- Is the sink staying where it is? If not, what is the plumbing line for moving it?
- When are the waste and water points fixed, and when do you need the sink and tap model by?
- Undermount or top-mount, and on what worktop? If the top is laminate, how is the cut edge sealed?
- When is the worktop measured, and does the sink need to be on site that day?
- Is there hot water to the kitchen sink, and is there a socket in the sink cabinet?
- What is the base of the sink cabinet made of, and can the stop valves be reached easily?
- What does the 1-year warranty cover on the sink, tap and plumbing work, in writing?
What to do this week
- Measure your biggest pot or wok and choose the bowl size from it.
- Decide undermount or top-mount, and deck or wall tap, and write the models down.
- Photograph the cabinet under your current sink with the door open, including the pipes and the base panel.
We are an HDB Licensed Renovation Contractor, HB-09-5667H, and we handle the whole HDB permit application on our HDB jobs. Planning a new kitchen and not sure where the sink should go? WhatsApp us on 9107 2601 with your flat type, a photo of the current sink area and the sink you have in mind, and we will arrange a site visit. Any price depends on that visit. The countertop, carpentry and electrical rates are on our room cost calculator, the kitchen package tiers and the programme are on our 4-room HDB renovation cost page, and you can see the finished kitchen in this maisonette's project photos.