Kitchen Glass Sliding Door in an HDB Flat, Singapore: Track, Parking Wall and Floor Line to Settle Before Tiling
Pictured above: a glass-walled kitchen beside the dining table in one of our HDB flat projects. Clear glass runs from the floor to the ceiling, with glass doors and long bar handles in the middle, so the hob, the sink and the dish rack stay in view from the dining area while the kitchen can still be shut.
Many owners take the kitchen wall down for an open layout. Our 4-room HDB renovation cost page lists taking down the kitchen entrance wall for an open-concept layout among the common hacking works. Then the first plate of fried fish fills the living room, and the question becomes how to shut the kitchen again without losing the light and the view. A glass sliding door, or a glass wall with a door in it, is the usual answer.
This guide is for an HDB owner planning one. It uses only the rates and the programme already published on this site.
The short answer
- Decide how the door hangs before the floor is tiled and the ceiling is closed. A door hung from the top and a door running on a floor track need different work at different stages.
- Find out where the panel parks when it is open. It slides in front of a stretch of wall, and whatever is on that stretch gets covered.
- Measure what has to pass through. The fridge, the washing machine and anything going out to the service yard often go through this opening.
- Expect less smell, not no smell. A sliding door has gaps a framed swing door does not.
When it is decided: weeks 2 to 5, fitted in week 8
On our 4-room HDB renovation cost page, hacking is week 1; masonry, plumbing and electrical are weeks 2 to 3; waterproofing, tiling and the false ceiling are weeks 4 to 5; carpentry is weeks 6 to 7; and painting, doors and hardware, sanitary fittings and handover are week 8.
A glass door is measured and fitted late, once the opening, the floor and the ceiling are finished. But three things about it are fixed much earlier. The switches and sockets around the opening go in at the electrical stage. The floor under it is laid at the tiling stage. Whatever it hangs from is built before the ceiling closes.
First: is the wall coming out, or is the opening staying?
There are two common cases. In the first, the kitchen wall stays and its door opening gets a glass door, made to fit the opening. In the second, the wall is hacked and a glass wall goes in its place, with a sliding door in part of it. Then the width of the door is a choice, and so is how much of the glass is fixed.
Which walls can come out is a separate question with its own rules. Our guide to which HDB walls you can remove covers it. Settle that before you design the glass, because the answer decides which of the two cases you are in.
Hung from the top, or running on a floor track
A sliding glass panel is heavy, and its weight goes somewhere.
Top-hung. The panel hangs from a track fixed above the opening. The floor runs through clean, with nothing to step over or sweep around. The price of that is the fixing above: the track needs something solid to hold it, such as the concrete beam or slab, or a proper support built into the false ceiling. A track screwed into ceiling board alone is the wrong answer. So if a false ceiling is going in over the opening, the support for the track has to be in place before the ceiling is closed in weeks 4 to 5. Ask what your track will be fixed to, in those words.
Floor track. The panel runs on a rail on the floor. That rail is either set into the floor when it is tiled, so it sits level, or laid on top afterwards, which leaves a small lip. A lip at the kitchen door is something to trip over and a groove that collects crumbs, water and grease. If you choose a floor track, it is a tiling-stage decision, not a week 8 one.
Most top-hung glass doors still have a small floor guide to stop the panel swinging. Ask where it goes, so it does not end up in the middle of the path.
Where the panel parks
When a sliding door is open, the panel sits in front of the wall or the fixed glass beside the opening. Whatever is on that stretch is covered: the kitchen light switch, a socket, the end of a tall cabinet whose door now cannot open, the side of the fridge.
The usual mistake is the kitchen light switch: it sat beside the old swing door, and the new panel parks right over it. Look at your plan with the panel drawn in both positions, open and shut, and move any switch or socket that would be covered. That is done at the electrical stage, in weeks 2 to 3. Our room cost calculator lists a light point at $90 and a power point at $90, so you can see what an added point costs on our published rates.
The other way out is a pocket door, where the panel slides into a cavity inside the wall and disappears. That needs a wall built with the pocket in it, usually a partition rather than an existing brick wall, and it has to be planned before that wall is built. Our guide to drywall, glass and half-height partition walls covers the wall side.
Measure what has to pass through
In most HDB flats the service yard is reached through the kitchen. That means the fridge, the washing machine and anything going out to the yard pass through this opening, now and every time an appliance is replaced.
A glass wall with one sliding panel and one fixed panel gives you about half the width as a clear opening. Measure your fridge, including its handles and the door hinge, and the washing machine, and compare them with the clear opening of the design, not the width of the whole glass wall. If one does not fit, a wider sliding panel or two panels that part in the middle are easier to decide on paper than on site.
The floor line and the space above
The kitchen floor and the living room floor are often different finishes, or are being done in different ways: the kitchen re-tiled, the living room overlaid with vinyl. The line where they meet should fall under the glass, not a few centimetres into either room, and the two floors should finish at the same height. That line is drawn at the tiling stage. Our calculator lists floor tiling at $11.80 per sq ft, including waterproofing.
Above the opening, the track competes for space with whatever else runs there: aircon trunking, the cooker hood duct on its way to the window, a false ceiling edge, a curtain track on the living room side. Our guides to where the cooker hood, its socket and its duct go and to curtain tracks and aircon trunking deal with the same strip of ceiling from the other side.
The glass, and how much smell it stops
The glass. Ask for toughened safety glass, with the type and the thickness written on the quotation. Clear glass keeps the light, and in many kitchens the window is the only daylight in that part of the flat. Frosted glass hides the dish rack and the clutter on the worktop.
The smell. A sliding door cuts cooking smell and smoke a great deal, but it does not stop them. There are gaps at the edges and at the floor. If heavy frying is a daily thing, run the cooker hood, keep the kitchen window open so the hood has air to draw, and keep the door shut while you cook. Shutting the kitchen also keeps the aircon in the living room.
If a fully closed kitchen matters more than the view, a solid swing door is the simpler answer. It is the only door we publish a price for: on our room cost calculator a solid laminate door is $388 each including a lever lockset, a wooden door frame $180 each to supply and $180 each to install. Our guide on replacing a door or the frame too explains those lines.
What it costs
We publish no price for a glass sliding door or a glass kitchen wall. It depends on the width, the height, how it hangs, the glass and the frame, so it is priced from your opening after a site visit. What we do publish for the kitchen around it is on our 4-room HDB renovation cost page: as a standalone package, a basic kitchen renovation is $8,000 to $12,000, a standard one $12,000 to $18,000 and a premium one $18,000 to $25,000. The added points and the floor are on our room cost calculator.
Questions to put in writing
- Does the door hang from the top or run on a floor track?
- If top-hung, what is the track fixed to, and is that support in place before the ceiling is closed?
- If on a floor track, is the track set into the tiles or laid on top?
- Where does the panel park when open, and what does it cover there?
- What is the clear opening when the door is open, and will my fridge and washing machine pass through?
- What glass is it, what thickness, and is it toughened?
- Where does the floor guide go, and where do the two floor finishes meet?
- What does the 1-year warranty cover on the door and its track, in writing?
What to do this week
- Mark on your floor plan where the panel will sit when it is open, and list every switch and socket on that stretch of wall.
- Measure your fridge and washing machine, handles included.
- Decide whether the view or a closed kitchen matters more to you. That one answer decides between glass and a solid door.
We are an HDB Licensed Renovation Contractor, HB-09-5667H, and we handle the whole HDB permit application on our HDB jobs. Planning a glass door or a glass wall for your kitchen? WhatsApp us on 9107 2601 with your flat type, a photo of the kitchen opening from the living room side and whether the wall is staying, and we will arrange a site visit. Any price depends on that visit. The renovation programme and the kitchen packages are on our 4-room HDB renovation cost page, and you can see the finished glass-walled kitchen in this flat's project photos.