Contractor's progress update for job 17CBR: the Larry Contractors team posts dated photos from this renovation as each stage is done, newest first. For finished work, see the portfolio.
Lift structure formwork closed up and roof beam rebar in place, ready for inspection.
Hoisting beam rebar connections and ends checked by the RTO and cleared on site.
Roof beam rebar cages tied with 4 bars top and 4 at bottom, and wall rebar and formwork going up for the lift structure.
Lift column rebar is now up through the roof line.
Wall and column formwork propped and braced for the lift structure.
The lift shaft wall and columns are up, with scaffolding still in place.
Lift shaft column rebar and formwork checked and cleared on site.
Rebar tied and column formwork set for the lift structure.
Lift shaft opening with rebar and formwork checked on site.
Column formwork up and braced for the lift structure.
Rebar and formwork going in for the lift structure.
Columns are up, rebar mesh is in place, and engineers have done a thorough check — your lift shaft is taking shape.
Lift shaft work has started at 17CBR. The floor slab has been opened up, with scaffold barriers around the opening. The steel reinforcement bars and mesh are on site.
The Permit to Commence Work is in for 17CBR. It took months of applications and rejections to get here. The job is additions and alterations to an existing three-storey semi-detached house. Work can start on site now.
The permit paperwork for the 17CBR job is in. The works are additions and alterations to an existing 3-storey semi-detached house. This one is a record of the submission, not a site photo.